11. The key difference between Work performance data and Work performance Measurement is :
A. There are no differences - both are the same
B. Work performance data is the 'as of now' status of deliverables while Work performance measurement is a comparison between planned Vs Actuals
C. Work performance measurement is the 'as of now' status of deliverables while Work performance data is a comparison between planned Vs Actuals
D. Work performance data are the planned objectives
Ans: b

12. Decomposition is best described as:
A. Creating control accounts.
B. Creating work packages.
C. Breaking down deliverables into smaller work packages so they can be better planned
D. Planning and scheduling of work packages
Ans: c

13. Which of the following activities is not performed as a part of Project Closure ?
A. Ensure all the deliverables as per contract are met
B. Create lessons learned and update Organizational Process Assets
C. Formal acceptance
D. Verify scope
Ans: d

14.  Your team has delivered phase one to the client. Based on client feedback and issues found by client - you decide to do some introspection to identify root causes so that the subsequent deliverables do not face the same issues. What techniques would you choose to apply ?
A. Perform Quality Audits
B. Review Activity Network Diagrams
C. Lookup Process decision program charts
D. Process Analysis
Ans: d