Top 9 SAP PS Objective type Questions and Answers

1. With reference to Organization Assignments in Project Systems, which of the following 
statements are true?
a.        Controlling Area & Company Code assignments is mandatory at Project Definition level.
b.        Currency can be changed Only if the controlling area does not allow different company code currencies.
c.         Business area assignment is mandatory at Project Definition level.
d.        Profit center assignment is mandatory at Project Definition level.
Answer: a, b

2. All the currency-dependent data in the Project System is managed in three different currencies in parallel. These are;
a.        Business Area Currency
b.        Controlling area currency
c.        Object Currency
d.        Transaction currency
Answer: b, c, d

3. Project System has its own Organizational structure, which can be a matrix structure.
a. True
b. False
Answer: B

4. Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project. Which of the following can be assigned?
a. Persons
b. Organizational units
c. Jobs
d. Positions
Answer: a, b, d

5. What are the pre-requisites for distributing work to HR Resources?
a. In Customizing for the Project System, you must have defined profiles for workforce planning in Resources.
b. Assigned work centers to the internally processed activities.
c. Assigned one or more labor capacity to a work center.
Answer: a, b